This 11 km section of the $91 M Waikato Expressway
traversed some geotechnically demanding terrain.
The northern part of the route was jammed between
several large block landslides, the North Island
Main Trunk Railway and the Waikato River.
Tonkin & Taylor was instrumental in the adoption
of an innovative route option in the northern section,
which bypassed the railway, excavation of the toe
of the landslides and unloaded the head of many
landslides, thereby significantly mitigating short and
long term risk for Transit NZ and their contractors.
Nelson City Council, Roading Retaining Wall Survey
Client : Nelson City Council.
Discipline : Multi
Under new Government Legislation NCC were required to assess their assets with regard to remaining asset life and current valuation. Tonkin & Taylor were contracted to put together a database of NCC’s roading retaining walls. An assessment of each walls condition, its spatial location and a risk assessment was undertaken at the same time.
Client :City Solutions, Christchurch City Council.
Discipline : Multi
The Blenheim Road deviation leads traffic from Blenheim Road to Moorhouse Avenue, away from the previous overbridge to Deans Avenue. A reinforced-earth embankment and overbridge were constructed to take the deviation over the existing main trunk railway line. Due to loose sand and silt in the upper 10 m of the foundation soils, significant settlement (up to 300 mm) was predicted under the overbridge abutments. Therefore a key factor driving design for this project was to ensure vertical clearance between the overbridge and railway would satisfy operational requirements for the lifetime of the structure. To mitigate this settlement risk, an extensive preloading program was developed, which generated settlement of up to 200 mm. Liquefaction was also a significant issue for the project, as the seismic vulnerability of the existing overbridge was a major reason for the deviation project. Liquefaction and settlement risk at the abutments was mitigated using vibroreplacement (gravel columns). Gravel columns were a very cost effective solution when compared to conventional piled abutment options.
The scheme provides for the widening of the existing State Highway 20 between Walmsley Road and Queenstown Road.
The project involves modification and rebuilding of several existing motorway bridges, foot bridges and the construction of a duplicate bridge over the Manukau Harbour. A new interchange will also be constructed at Gloucester Park. Significant environmental design and construction constraints have dictated that a low level embankment constructed with ultra light weight polystyrene fill will be required for the new carriageways crossing the unfilled crater within the Hopua Tuff ring.
The 4 laning of SH 1 from the weighstation to the
Paremata overbridge was a controversial project to
improve the traffi c flows on SH1. The project was
subject to strict resource consent and designation
conditions. The construction area was adjacent to
the nationally significant Taupo swamp, Porirua
Harbour and Paremata Estuary.
Given the public interest in the project it was
essential that environmental management of
construction activities ensured full compliance with
the conditions.
The road embankment was constructed over
peat deposits. This required monitoring and
interpretation of settlement and groundwater data.
Advice was also provided on excavation stability
within these very weak deposits.
The $30 M Hewletts Rd Bridge project was completed in 2006 and provides a flyover to improve traffic flows on the Mt Maunganui site of the Tauranga Harbour Bridge. Tonkin & Taylor were principal designers as part of the design build contracts undertaken by Fulton Hogan - Smithbridge joint venture. The ground conditions
in the area include deep sand deposits which
exhibit susceptibility to liquefaction under
seismic loading.
Client :Transit New Zealand and Manukau City Council
(through GHD Ltd).
Discipline : Multi
The project provides a roading link between the
Southern Motorway (SH1) and the new Highbrook
Business Park on the Waiouru Peninsula, Auckland.
The scope involves widening of SH1, including
widening of the causeway and bridge across the
Tamaki River, a new interchange of Highbrook
Drive with SH1, a new multi-span bridge across
Otara Creek and Highbrook Drive itself.
Tonkin & Taylor provided the structural and geotechnical engineering services for the $1.9M tramway extension project. The 600 m long tramway extended across an old landfill and a 90 year old cast iron sewer, both of which presented significant geotechnical risk. T&T worked with the client to provide innovative and economical solutions for the tram track, including the use of an ‘impact roller’ and a polystyrene fill embankment. The design solutions provided MOTAT with significant cost savings over conventionally designed piled and DC options.
Client : Works Infrastructure and Transit New Zealand.
Discipline : Multi
The Greenhithe section of the Upper Harbour
Highway runs from Constellation Drive at the
north eastern end to the Upper Harbour Bridge
at the south western end. The project involves
some high earth embankments (27 m) over soft
ground, three interchange bridges and several
MSE walls. A feature of the design is the range
of special measures employed to enable
construction with wet fill soils, including use of
geo-grids, lime treatment and a specification to
meet the design requirements.
Tonkin & Taylor operates three falling weight deflectometers for structural testing of pavements. A portable Geobeam Deflectometer has also been developed by T&T which provides deflection based profiling for analysis of pavement layer stiffnesses, residual life and assessment of rehabilitation options to achieve projected loading.
The MacKays Crossing project north of Wellington
involves construction of a 4 lane rail overbridge and
2 km of realignment of SH1 at a cost of $21 M. The
works include environmental mitigation measures
and enhancement of the wetlands. Much of the cut
is underlain by deep peat deposits and the works
needed to be undertaken adjacent to live rail and a
sensitive gas pipeline.
The Northern Gateway project involves construction
of a 7 km section of motorway between Orewa and
Puhoi. The 7.5 km route crosses areas of native
bush which has high environmental sensitivity
and steep topography requiring a number of major
bridges, tunnels and deep cut/fills. The project is
currently the largest roading works in NZ valued
at $350M. Special attention has been given to
protection of the area and includes eco-viaducts,
fish passages, water quality treatment facilities
and the use of construction methods which have
minimised disturbance of the bush. Tonkin & Taylor
has been a full alliance member of the project
design and construction team.
The $143 m PJK Expressway was constructed as
a jointly funded toll highway project by Tauranga
City and Transit NZ. At the time of construction
(1999 - 2003), it was New Zealand’s largest roading
project. The work involved construction of 14 km
of pavement with three intersecting roads over a
20 m deep area of swamp and included a major
grade separated interchange with bridge sections
of up to 300 m length and piles up to 40 m deep
together with a number of other bridge and
retaining structures as well as deep
embankments and sections.
The bridge was part of a controversial programme
of works to improve SH 1 in the Plimmerton/
Paremata area. The project was subject to strict
resource consent and designation conditions. The
construction envelope was limited.
Given the public interest in the project it was
essential that environmental management of
construction activities ensured full compliance
with the conditions.
An alternative ground improvement design was
developed to reduce cost and environmental
impacts and to allow more flexibility in
construction programming.
The Rewa Bridge project was a design-build contract undertaken for the Government of Fiji Public Works Department which involved the construction of a 425 m long, four-lane bridge in Nausori, Fiji. The abutment and pier foundations consisted of 204 no. 610 mm diameter steel tube piles driven to depths of 50 m.
The Tauranga Harbour Link Stage II project
involved construction of a duplicate bridge adjacent
to the existing harbour crossing and an elevated
expressway connecting the crossings to the
existing expressway. The project includes the 470 m incrementally
launched harbour bridge and the 600 m elevated
viaduct. Ground conditions for the project include
deep soils with significant liquefaction potential.
Tonkin & Taylor has provided highly innovative
cutting edge design as part of the design build
team. This has included the application of
numerous technologies new to New Zealand such
as piling under bentonite slurry.
T&T also implemented design solutions that are state
of the art internationally including vertical drains and
raked timber piles for liquefaction mitigation.